System and Method for An Adaptive Scheduling System
Architecture
Abstract
The disclosed embodiments describe an automatic, adaptive system
and method for efficiently and effectively scheduling advertising
spots in commercial break locations across various networks, zones,
channels, dates, times, and specific products, for example. The
disclosed embodiments make use of fixed and relative factors, that
may be user-defined, which assign a "cost" to one or more
particular breaks which thereby allow for quick and accurate
scheduling of spots. The "costs" may represent a value, or
desirability, of a break for the advertiser and may be a function
of both the fixed and relative factors. The fixed and relative
factors may be configurable and may change for different
advertising clients, different contract lines, different networks,
different spot placement, etc. The placement of spots may be
accomplished through the use of an ordered list which may be
generated based on a number of inputs that may be user-selected. A
non-limiting example of user inputs may include: spot length, spot
cost, contract line priority, beginning date/time of contract line,
ending date/time of contract line, a predefined value index for the
client, and contract line number, among others.
Inventors: |
Schepers; Trisha; (Byron
Center, MI) ; Falk; Stephen; (Grand Rapids,
MI) |
Assignee: |
Harris Corporation
Melbourne
FL
|
Family ID: |
39677288 |
Appl. No.: |
12/974279 |
Filed: |
December 21, 2010 |
Related U.S. Patent Documents
|
|
|
|
|
|
Application
Number |
Filing Date |
Patent Number |
|
|
11701422 |
Feb 2, 2007 |
|
|
|
12974279 |
|
|
|
|
Current U.S.
Class: |
705/7.12 ;
705/500 |
Current CPC
Class: |
H04N 21/44016 20130101;
H04N 21/26208 20130101; H04N 7/165 20130101; G06Q 10/0631 20130101;
H04N 21/2668 20130101; H04N 21/8455 20130101; G06Q 99/00 20130101;
H04H 60/06 20130101; G06Q 30/02 20130101; H04N 21/23424 20130101;
H04N 21/812 20130101 |
Class at
Publication: |
705/7.12 ;
705/500 |
International
Class: |
G06Q 30/00 20060101
G06Q030/00; G06Q 10/00 20060101 G06Q010/00 |
Claims
1. A method for scheduling, comprising: (a) prioritizing a list of
networks for scheduling advertising spots ("spots"); (b)
determining if one or more networks on said list of networks
requires spot scheduling; (c) selecting, from said list of
networks, a network which requires spot scheduling; (d) determining
one or more commercial break locations ("breaks") on said selected
network; (e) assigning a cost to ones of said one or more breaks,
wherein said assigned cost is a function of a user-defined
predetermined fixed parameter; and (f) scheduling a selected spot
for one of said breaks based on said assigned cost.
2. The method of claim 1 wherein step (b) further comprises
displaying a network spot schedule if none of said networks
requires spot scheduling.
3. The method of claim 1 wherein step (c) further comprises: (A)
obtaining scheduling information for said selected network; (B)
generating an ordered list of spots; (C) selecting a contract line
from said ordered list, said contract line containing one or more
spots to be scheduled; and (D) selecting a spot for scheduling.
4. The method of claim 3 further comprising: (g) determining if
there is an additional spot to be scheduled from said contract
line; and (h) assigning a second cost to ones of said one or more
breaks, wherein said second cost is a function of a predetermined
relative parameter.
5. The method of claim 1 further comprising: (g) if said assigned
cost is above a predetermined threshold: (A) determining if a bump
candidate exists; (B) if no bump candidate exists; logging said
selected spot as an exception; and (C) if a bump candidate exists;
bumping said bump candidate from its associated break, placing said
bump candidate on said ordered list of spots, and scheduling said
selected spot in said break associated with said bump
candidate.
6. The method of claim 5 further comprising: (D) scheduling a spot
logged as an exception in one of said breaks that is not scheduled
with a spot.
7. The method of claim 1 wherein each of said spots has an
associated scheduling factor.
8. The method of claim 1 wherein said fixed parameter is selected
from the group consisting of: day of the week, day part,
availability of a commercial break location, and combinations
thereof.
9. The method of claim 8 wherein said day part parameter is
selected from the group consisting of: an overnight parameter, a
morning parameter, an afternoon parameter, a prime parameter, and
combinations thereof.
10. The method of claim 4 wherein said relative parameter is
selected from the group consisting of: interval of time between
said first break and said second break, difference in day part of
said first break and day part of said second break, difference
between day of the week of said first break and day of the week of
said second break, difference between a first product associated
with said first spot and a second product associated with said
second spot, and combinations thereof.
11. The method of claim 7 wherein said scheduling factor is
selected from the group consisting of: ranking identification,
product type, stop time, start, time, stop date, start date, cost,
contract line identification number, line number, client value, and
combinations thereof.
12. A method for scheduling, comprising: (a) prioritizing a list of
networks for scheduling advertising spots ("spots"); (b)
determining if one or more networks on said list of networks
requires spot scheduling: (A) if none of said networks requires
spot scheduling, displaying a network spot schedule; (B) if one of
said networks requires spot scheduling; selecting a first network;
(C) obtaining scheduling information; (D) generating an ordered
list of spots; (E) selecting a first contract line from said
ordered list, said first contract line containing one or more spots
to be scheduled; and (F) selecting a first one of said spots
("first spot"); (c) based on said scheduling information,
determining if one or more commercial break locations ("breaks") on
said selected network are acceptable for placing said first spot,
wherein each of said breaks has an assigned first cost which is a
function of a predetermined fixed parameter, and wherein said fixed
parameter is user defined: (A) if one or more acceptable breaks is
determined to exist, scheduling said first spot in one of the
acceptable breaks; and (B) if one or more acceptable breaks is
determined to not exist: (1) determining if a bump candidate
exists; (2) if no bump candidate exists; logging said first spot as
an exception; and (3) if a bump candidate exists; bumping said bump
candidate from its associated break, placing said bump candidate on
said ordered list of spots, and scheduling said first spot in said
break associated with the bump candidate; (d) determining if there
are any additional spots associated with said contract line: (A) if
there are additional spots associated with said contract line,
selecting a second spot from said first contract line and repeating
(c) through (d) for said second spot in place of said first spot;
and (B) if there are no additional spots associated with said first
contract line, check and assign ad copy to all scheduled spots; and
(e) determining if there are additional contract lines: (A) if
there are additional contract lines, selecting a second contract
line and repeating (c) through (e) for said second contract line in
place of said first contract line; and (B) if there are no
additional contract lines, placing spots logged as exceptions and
repeating (b) through (e) for a second network in place of said
first network.
13. A system for scheduling, comprising: circuitry for prioritizing
a list of networks for scheduling advertising spots ("spots");
circuitry for determining if one or more networks on said list of
networks requires spot scheduling; circuitry for selecting, from
said list of networks, a network which requires spot scheduling;
circuitry for determining one or more commercial break locations
("breaks") on said selected network; circuitry for assigning a cost
to ones of said one or more breaks, wherein said assigned cost is a
function of a user-defined predetermined fixed parameter; and
circuitry for scheduling a selected spot for one of said breaks
based on said assigned cost.
14. The system of claim 13 further comprising a display for
displaying a network spot schedule if none of said networks
requires spot scheduling.
15. The system of claim 13 further comprising: circuitry for
obtaining scheduling information for said selected network;
circuitry for generating an ordered list of spots; circuitry for
selecting a contract line from said ordered list, said contract
line containing one or more spots to be scheduled; and circuitry
for selecting a spot for scheduling.
16. The system of claim 15 further comprising: circuitry for
determining if there is an additional spot to be scheduled from
said contract line; and circuitry for assigning a second cost to
ones of said one or more breaks, wherein said second cost is a
function of a predetermined relative parameter.
17. The system of claim 13 further comprising: circuitry for
determining if said assigned cost is above a predetermined
threshold, comprising: circuitry for determining if a bump
candidate exists; circuitry for logging said selected spot as an
exception if no bump candidate exists; and if a bump candidate
exists, circuitry for bumping said bump candidate from its
associated break, placing said bump candidate on said ordered list
of spots, and scheduling said selected spot in said break
associated with said bump candidate.
18. The system of claim 17 further comprising: circuitry for
scheduling a spot logged as an exception in one of said breaks that
is not scheduled with a spot.
19. The system of claim 13 wherein each of said spots has an
associated scheduling factor.
20. The system of claim 13 wherein said fixed parameter is selected
from the group consisting of: day of the week, day part,
availability of a commercial break location, and combinations
thereof.
21. The system of claim 20 wherein said day part parameter is
selected from the group consisting of: an overnight parameter, a
morning parameter, an afternoon parameter, a prime parameter, and
combinations thereof.
22. The system of claim 16 wherein said relative parameter is
selected from the group consisting of: interval of time between
said first break and said second break, difference in day part of
said first break and day part of said second break, difference
between day of the week of said first break and day of the week of
said second break, difference between a first product associated
with said first spot and a second product associated with said
second spot, and combinations thereof.
23. The system of claim 19 wherein said scheduling factor is
selected from the group consisting of: ranking identification,
product type, stop time, start, time, stop date, start date, cost,
contract line identification number, line number, client value, and
combinations thereof.
Description
CROSS-REFERENCE TO RELATED APPLICATIONS
[0001] The present application is a divisional application of
co-pending U.S. patent application Ser. No. 11/701,422 filed 2 Feb.
2007 and entitled "System and Method for an Adaptive Scheduling
System Architecture", the entirety of which is hereby incorporated
herein by reference. Additionally, cross-reference is hereby made
to co-pending U.S. patent application Ser. No. 11/701,423 filed 2
Feb. 2007 and entitled "System and Method for an Adaptive
Scheduling System Architecture", the entirety of which is hereby
incorporated by reference.
BACKGROUND
[0002] Current scheduling systems for placing commercial messages,
sometimes referred to herein as "advertising spots" or "spots" in
communication media such as television (e.g., broadcast, cable,
etc.), radio (e.g., broadcast, satellite, etc.), wireless access
(e.g., hand-held devices like personal digital assistants, cell
phones, iPods, Blackberries, etc.) or other media, are incapable of
meeting the burgeoning demand of new networks and channels for
advertising or the plethora of advertising spots that need to be
scheduled. Additionally, the complexity with which current
advertising is designed to be scheduled is another factor that is
stretching the limits of current scheduling systems.
[0003] Current scheduling systems, either manual or "automatic",
typically rely on only two inputs for determining when an
advertising spot is to be scheduled: rate (cost) and contract line
priority. As is known in the art, the cost of airing an advertising
spot may vary depending on a number of factors, the most common
being the day of the week and the time of the day the spot is
aired. For example, a spot aired in "prime time" when the potential
audience is large is more expensive than airing the spot during the
middle of the night when the potential audience is smaller
Priorities in prior art scheduling systems are generally set and
static and therefore require a large amount of time and effort to
change. Additionally, if a higher-priority advertising spot were to
try to be scheduled after a lower-priority spot was already
scheduled, typical prior art systems typically would have to
schedule the higher-priority spot around the lower-priority spot,
thereby turning the priorities upside-down, or spend a lot of time
and effort manually rearranging the schedule to account for the
placement of the higher-priority spot. This is inefficient,
ineffective, and expensive. Obviously, there is a need for an
advertising spot scheduling system that can take into account more
than two parameters, allow scheduling of multiple advertising spots
on multiple forms of media, each having a large number of networks
and/or channels, and be able to adapt to changing conditions.
[0004] The present disclosure takes into account the complexity
inherent in current and future advertising scheduling systems and
methods. For example, the present disclosure may make use of a
ranking algorithm that ranks available commercial breaks in
communication media program scheduling and may take into account a
variety of factors, some fixed factors and some relative factors,
as herein described, in performing such ranking Furthermore, the
selection of which factors to use and the weight given to each
factor may be user-defined rather than preset by, for example, a
network, a scheduling entity, or a governing body. By using a
variety of factors, which may or may not be user-defined, the
commercial break locations ("breaks") where spots are to be placed
("scheduled") may be tailored to better meet the needs of the
advertiser.
[0005] Additionally, with the advent of cable television systems
and the plethora of networks now available for viewers to watch,
the prior art systems of manually scheduling spots or automatically
scheduling spots according to fixed rules, becomes an intractable
problem which the prior art systems cannot handle efficiently or
effectively.
[0006] Accordingly, it is an object of the present disclosure to
obviate the problems of the prior art and to provide a method and
system of scheduling where an ordered list of advertising spots to
be scheduled is provided where each spot has an associated
scheduling factor, a first one of the spots is selected, one or
more breaks for one or more networks are selected, a first cost for
each of the breaks is determined as a function of a predetermined
algorithm, and the first spot is assigned (i.e., "placed" or
"scheduled") to one of the breaks which has a lowest first
cost.
[0007] It is also an object of the present disclosure to provide a
method and system of scheduling where an ordered list of spots is
generated from a select group of spots to be scheduled, where each
of the spots has an associated scheduling factor, and a first spot
is selected and assigned to a first break chosen from multiple
breaks as a function of a first cost assigned individually to each
of the multiple breaks, where each of the first costs is a function
of a predetermined fixed parameter. Additionally, if during the
method of scheduling a second spot it is determined that no
unassigned breaks have a second cost less than a predetermined
amount thereby preventing the second spot from being assigned to
one of the unassigned breaks, determining the relative rankings of
the first and second spots and if the ranking of the second spot is
greater than the ranking of the first spot, bumping the first spot
from the first break and assigning the second spot to the first
break. However, if the ranking of the second spot is not greater
than the ranking of the first spot, place the second spot on an
exceptions list to be placed later.
[0008] It is another object of the present disclosure to provide a
computer program for scheduling where the computer program includes
computer-readable code including program instructions for providing
an ordered list spots to be scheduled where each spot has an
associated scheduling factor, selecting a first one of the spots,
providing multiple breaks for one or more networks, determining a
first cost for each of the breaks as a function of a predetermined
algorithm, and assigning the first spot to one of the breaks which
has a lowest first cost.
[0009] It is a further object of the present disclosure to provide
a system for scheduling including a database comprising (a) an
ordered list of spots to be scheduled where each spot has an
associated scheduling factor, and (b) a plurality of breaks for one
or more networks, and a microprocessor operatively connected to the
database, where the microprocessor comprises (a) circuitry for
selecting a first spot, (b) circuitry for determining a first cost
for each of the breaks as a function of a predetermined algorithm,
and (c) circuitry for assigning the first spot to one of the breaks
which has a lowest first cost. Alternatively, the circuitry for
assigning the first spot may assign the first spot to one of the
breaks that has a first cost less than a first predetermined
amount. Additionally, the system for scheduling may include
circuitry for removing the first spot from the ordered list of
spots.
[0010] Furthermore, the system for scheduling may include circuitry
for selecting a second spot, circuitry for determining a second
cost for unassigned breaks as a function of the first cost and as a
function of a predetermined relative parameter, and circuitry for
assigning the second spot to one of the unassigned breaks which has
wither a lowest second cost or a second cost that is less than a
second predetermined amount. In addition, the circuitry for
assigning the second spot may determine that no unassigned breaks
have a second cost less than a second predetermined amount thereby
preventing the second spot from being assigned to one of the
unassigned breaks, and may determine that the second spot has a
ranking greater than a ranking for the first spot, bumps the first
spot from the first break, and assigns the second spot to the first
break. Alternatively, the circuitry for assigning the second spot
may determine that no unassigned breaks have a second cost less
than a second predetermined amount thereby preventing the second
spot from being assigned to one of the unassigned breaks, may
determine that the second spot has a ranking less than a ranking
for the first spot, and may place the second spot on an exceptions
list, and may remove the second spot from the ordered list of
spots. Additionally, the circuitry for assigning the second spot
may assign the second spot to any one of the unassigned breaks.
Still further, the system for scheduling may include circuitry for
assigning advertising ("ad") copy to the spots.
[0011] It is yet another object of the present disclosure to
provide a method and system for scheduling including prioritizing a
list of networks for scheduling spots; determining if one or more
networks on the list of networks requires spot scheduling such that
(a) if none of the networks requires spot scheduling, displaying a
network spot schedule, or (b) if one of the networks requires spot
scheduling then (i) selecting a first network, (ii) obtaining
scheduling information, (iii) generating an ordered list of spots,
(iv) selecting a first contract line from the ordered list, where
the first contract line contains one or more spots to be scheduled,
and (v) selecting a first spot; based on the scheduling
information, determining if one or more breaks on the selected
network are acceptable for placing the first spot, where (a) if one
or more acceptable breaks is determined to exist, scheduling the
first spot in one of the acceptable breaks, or (b) if one or more
acceptable breaks is determined to not exist then (i) determining
if a bump candidate exists, (ii) if no bump candidate exists then
logging the first spot as an exception, and (iii) if a bump
candidate exists, bumping the bump candidate from its associated
break, placing the bump candidate on the ordered list of spots, and
scheduling the first spot in the break associated with the bump
candidate; determining if there are any additional spots associated
with the contract line where (a)if there are additional spots
associated with the contract line, selecting a second spot from the
first contract line and repeating the method for the second spot,
or (b) if there are no additional spots associated with the first
contract line, check and assign ad copy to all scheduled spots; and
determining if there are additional contract lines, where (a) if
there are additional contract lines, selecting a second contract
line and repeating the method for the second contract line, or if
there are no additional contract lines, placing spots logged as
exceptions and repeating the method for a second network.
BRIEF DESCRIPTION OF THE DRAWINGS
[0012] FIG. 1a is a first part of a flow diagram of a scheduling
method according to an embodiment of the disclosure.
[0013] FIG. 1b is a second part of a flow diagram of a scheduling
method according to an embodiment of the disclosure.
[0014] FIG. 2 is a flow diagram of a scheduling method according to
an embodiment of the disclosure.
[0015] FIG. 3a is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0016] FIG. 3b is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0017] FIG. 3c is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0018] FIG. 3d is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0019] FIG. 3e is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0020] FIG. 3f is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0021] FIG. 4a is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0022] FIG. 4b is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0023] FIG. 4c is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0024] FIG. 4d is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0025] FIG. 4e is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0026] FIG. 4f is a flow diagram of a scheduling method according
to an embodiment of the disclosure.
[0027] FIGS. 5a through 5k illustrate an example of spot scheduling
according to an embodiment of the disclosure.
[0028] FIG. 6 is illustrative of an exemplary graphical user
interface according to an embodiment of the disclosure.
[0029] FIG. 7 is illustrative of an exemplary graphical user
interface according to an embodiment of the disclosure.
[0030] FIG. 8 is illustrative of an exemplary graphical user
interface according to an embodiment of the disclosure.
[0031] FIG. 9 is illustrative of an exemplary graphical user
interface according to an embodiment of the disclosure.
[0032] FIG. 10 is a block diagram of a scheduling system according
to an embodiment of the disclosure.
DETAILED DESCRIPTION
[0033] With the advent of communication signals being carried by,
for example, cable systems, telephony networks, the internet and
other computer networks, and satellite systems, for display to
viewers via standard television interfaces, computer interfaces,
and other non-standard television interfaces (e.g., personal
digital assistants, cell phones, iPods, Blackberries, etc.), the
opportunity and demand for scheduling advertising spots is ever
increasing. In order to meet the demand, the disclosed embodiments
describe a variety of systems and methods capable of efficiently
and effectively scheduling spots in commercial break locations
("breaks") for the large number of networks for which spots need to
be scheduled. The disclosed embodiments may make use of fixed and
relative factors (sometimes referred to herein as "fixed
parameters" and "relative parameters", respectively), that may be
user-defined, in order to quickly and accurately schedule
advertiser's spots at the dates, times, and for the channels that
the advertisers desire.
[0034] The novel scheduling method, sometimes referred to herein as
"Adaptive Scheduling", allows for a number of advantages not
available in prior art manual and/or automatic scheduling systems,
such as, for example, the elimination of traditional separate
processes for roadblock scheduling (i.e., placing the same spot in
the same break time for multiple channels so that viewers on the
multiple channels each see the same spot), the ability for the
advertiser to have a hand in setting the goals/costs of the
advertising campaign; reducing manual scheduling of exceptions
(i.e., spots that cannot be placed due to a lack of breaks meeting
the advertiser's preferred scheduling criteria) due to a more
effective placement of spots, and reducing the overall time
required to schedule spots.
[0035] As further discussed herein, specifically with reference to
FIGS. 5a through 5k, the fixed factors and the relative factors may
be user-defined. Fixed factors and relative factors are "costs"
assigned to a break. These "costs" may represent a value, or
desirability of, a break for the advertiser. These factors may be
used to achieve an appropriate vertical and horizontal rotation and
overall spot placement. Fixed factors may be the same regardless of
which spot is being placed. Relative factors may vary as spots are
placed. The cost of a break may be a function of both the fixed and
relative factors. The fixed and relative factors may be
configurable and may change for different advertising clients,
different contract lines, different networks, different spot
placement, etc.
[0036] Additionally, the placement of spots may be accomplished
through the use of an ordered list, sometimes referred to herein as
an "Adaptive Scheduling Order by Clause" or an "AS Order by
Clause", which may be generated based on a number of inputs that
may be user-selected. A non-limiting example of user inputs may
include: spot length, spot cost, contract line ranking, beginning
date/time of contract line, ending date/time of contract line, a
predefined value index for the client, ranking value, contract line
number, etc. The AS Order by Clause may be used in the
determination of the order in which spots are placed by, for
example, ordering the various contract lines and/or ordering the
various spots to be placed within one or more contract lines.
[0037] FIGS. 1a and 1b combined illustrate a method for scheduling
spots according to an embodiment of the disclosure. The method may
be carried out by a computer program executing programmable
instructions on a microprocessor-based system. The method
illustrated in FIGS. 1a and 1b may include three loops, as shown in
the Figures, which may be referred to as the Network Loop, and Spot
Loop, and the Contract Line loop. Referring now to FIG. 1a, at
block 100 multiple networks for which spots are to be scheduled may
be prioritized. At block 110, a decision may be made as to whether
there are additional networks on which to schedule spots. If all
the networks for which spots are to be scheduled have been
scheduled, then the procedure may end and a display of the schedule
for one or more of the networks may be created, printed out,
stored, etc. If there are more networks for which spots need to be
scheduled, at block 111 one of the networks that need to be
scheduled is selected. At block 112 existing information may be
accessed and/or loaded. This information may include, for example,
the network's programming schedule, the available breaks, and any
special events that may need to be taken into account. At block 113
new information may be accessed and/or loaded. This new information
may include, for example, new programming for the network,
Interconnect updates (where an Interconnect, as is known in the
art, is an entity that may reserve a portion of the breaks for a
given network or networks for the exclusive use by the
Interconnect), etc. It will be understood by those of skill in the
art that the above instances are only exemplary in nature and are
not intended in any way to limit the disclosure.
[0038] Referring now to FIG. 1b, after block 113, the procedure
goes to block 114 where a list of required spots may be generated.
This list, sometimes referred to herein as an "ordered list" may be
ordered and/or prioritized by a number of inputs, such as the
aforementioned inputs for the AS Order by Clause. Once the ordered
list is generated, at block 115 a contract line may be selected and
at block 116 a spot may be selected from the selected contract
line.
[0039] At block 120 a determination may be made regarding possible
locations for the spot to be scheduled, i.e., a determination may
be made as to which breaks meet the criteria for placement of the
spot. The criteria may include fixed and relative parameters and/or
other factors including, but not limited to, start/stop date and
time for the spot, availability of the spot and/or break for
scheduling, program name and/or type associated with the break,
product type associated with the spot, product conflict with the
name/type of program associated with the break, association between
the product associated with the spot and the type of program
associated with the break, minimum/maximum date/time separation
between the spot and types of programs that may conflict with the
spot, separation between the client's spot and a spot placed by
another client, etc. The fixed and relative parameters may be taken
into account in this step of the procedure as will be discussed in
more detail below with respect to FIGS. 5a through 5k. If one or
more of the breaks meets the criteria for placing the spot, the
spot is placed in one (or more) of the breaks at block 121. If none
of the breaks meet the criteria for placing the spot, then a "bump
candidate" is sought at block 130. A bump candidate may be a placed
spot that has a lower ranking than the current spot to be placed.
Additionally, the bump candidate may be placed in a break that
meets the criteria for the current spot to be placed.
Alternatively, the bump candidate may be placed in a break that is
a predetermined amount below the minimum criteria for the current
spot to be placed. If a bump candidate is found, then at block 131
the bump candidate may be bumped, i.e., removed from the break it
currently occupies, at block 132 the bump candidate may be placed
on the spot list (the ordered list) to be selected for scheduling
later, and at block 121 the current spot to be placed may be placed
in the break that was occupied by the bump candidate. If a bump
candidate is not found, then the current spot to be placed is
entered onto an exceptions list so that the current spot may be
placed, for example, in the best available break as discussed
below.
[0040] At block 140, a determination is made as to whether the spot
that was placed or entered onto the exceptions list is the last
spot for the current contract line. If the placed/excepted spot is
not the last spot for the current contract line, then the next spot
for the current contract line is selected at block 116 (thereby
closing the Spot Loop) and the above procedure may be repeated for
this newly-selected spot. If the placed/excepted spot is the last
spot for the current contract line, then advertising copy is
checked at block 141 and advertising copy is assigned at block 142,
as is known in the art, for each of the spots on the current
contract line.
[0041] At block 150, a determination is made as to whether the
current contract line is the last contract line having spots that
need to be scheduled. If the current contract line is not the last
contract line having spots that need to be scheduled, then the next
contract line is selected at block 115 (thereby closing the
Contract Loop) and the above procedure may be repeated for this
newly-selected contract line. If the current contract line is the
last contract line having spots that need to be scheduled, then
those spots on the exception list, such as the spots placed on the
exception list in block 133 above, may be placed at block 151.
After the excepted spots are placed, a determination is made at
block 110 as to whether there are additional networks for which
spots need to be scheduled. If there are additional networks for
which spots need to be scheduled, a new network is selected at
block 111 (thereby closing the Network Loop) and the above
procedure may be repeated for this newly-selected network. If there
are no additional networks for which spots need to be scheduled,
then the procedure may end at block 117 and a display of the
schedule for one or more of the networks may be created, printed
out, stored, etc., as discussed above.
[0042] With reference now to FIG. 2, a different embodiment of a
system and method for scheduling spots is disclosed. At block 200 a
network for scheduling spots is selected. At block 201, existing
and new information and updates for programming on the network are
checked and added for decision making. At block 202, a spot list is
generated, similar to the "ordered list" discussed above with
respect to FIGS. 1a and 1b. At block 203, a spot is selected for
scheduling. At block 204, possible locations (i.e., breaks) for the
spot to be placed are determined. If possible breaks exist, the
spot may be placed in one or more of the possible breaks at block
205. If possible breaks do not exist, at block 209 a determination
is made as to whether lower ranking spots are already scheduled in
one or more breaks that meet the criteria for placing the current
spot (i.e., the lower ranking spot(s) occupies a break(s) that
meets the needs for scheduling the current spot or is sufficiently
close to meeting the needs for the scheduling the current spot). If
a lower ranking spot is scheduled in a break that meets the
criteria for placing the current spot, at block 210 the lower
ranking spot may be bumped and may be placed on the spot list for
later scheduling, and at block 205 the current spot may be place in
the now vacant break. If a lower ranking spot is not scheduled in a
break that meets the criteria for placing the current spot, then at
block 211 the current spot may be added to an exceptions list (and
may be removed from the spot list).
[0043] At block 206, a determination may be made as to whether the
placed/excepted spot is the last spot to be scheduled for a
particular contract line. If the placed/excepted spot is not the
last spot to be scheduled for a particular contract line, then at
block 203 another spot is selected for scheduling and the above
procedure may be repeated for this newly-selected spot. If the
placed/excepted spot is the last spot to be scheduled for a
particular contract line, then at block 207 advertising copy
rotation is checked and advertising copy may be assigned to the
spots for the particular contract line, as is known in the art.
[0044] At block 208, a determination is made as to whether there
are additional spots to be scheduled for the current network. If
there are additional spots to be scheduled for the current network,
then at block 203 another spot is selected for scheduling and the
above procedure may be repeated for this newly-selected spot. If
there are no additional spots to be placed for the current network,
at block 212 the exceptions (e.g., from the exceptions list at
block 211 above) may be placed. At block 213, a determination is
made as to whether there are additional networks for which spots
need to be scheduled. If there are additional networks for which
spots need to be scheduled, then a network is selected for
scheduling at block 200 and the above procedure may be repeated for
this newly-selected network. If there are no further networks for
which spots need to be scheduled, then the procedure may end at
block 214 and a display of the schedule for one or more of the
networks may be created, printed out, stored, etc., as discussed
above.
[0045] With attention now directed to FIGS. 3a through 3f, these
figures represent a set of embodiments of the present disclosure,
such as may be implemented in hardware, software, computer
programs, circuitry, methodologies, etc., where like reference
numbers refer to like components/procedural stages. In FIG. 3a, an
ordered list of spots may be provided at block 301. The ordered
list of spots may be provided using an AS Order by Clause as
described elsewhere herein. At block 302 a first spot may be
selected from the ordered list. At block 303, breaks for scheduling
the first spot may be provided. At block 304, a first cost for each
of the breaks may be determined. At block 305 the first spot may be
assigned to one (or more) of the breaks, i.e., the "first break".
The assignment of the first spot to the first break may be made
with respect to fixed and/or relative parameters as discussed
herein.
[0046] Referring now to FIG. 3b, blocks 301 through 305 are as
described above for FIG. 3a. At block 306, the first block may be
removed from the ordered list. In FIG. 3c, blocks 301 through 305
are as described above. At block 307, a second spot may be selected
from the ordered list. At block 308, a second cost for each of the
breaks, or for only the unassigned breaks, may be determined. At
block 309 the second spot may be assigned to one (or more) of the
breaks, i.e., the "second break". The assignment of the second spot
to the second break may be made with respect to fixed and/or
relative parameters as discussed herein.
[0047] With reference now to FIG. 3d, blocks 301 through 305, 307,
and 308 are as described above. At block 310 a determination may be
made as to whether any available unassigned breaks exist that meet
the criteria for placing the second spot. It may be determined that
no unassigned breaks are available for placing the second spot,
i.e., none of the unassigned breaks meet the criteria for placing
the second spot. At block 311, a determination may be made that the
ranking of the second spot is greater than the ranking of the first
spot. At block 312, the first spot may be bumped from the first
break if, for example, the ranking of the second spot is greater
than the ranking of the first spot and perhaps, for example, that
the first break meets the criteria for placing the second spot. At
block 313, the second spot may be assigned to the first break.
[0048] Relating to FIG. 3e, blocks 301 through 305, 307, 308, and
310 are as described above. At block 314 a determination may be
made that the ranking of the second spot is less than the ranking
of the first spot. At block 315, if, for example, the ranking of
the second spot is less than the ranking of the first spot, the
second spot may be placed on an exceptions list (perhaps for later
scheduling) and removed from the ordered list. Referring now to
FIG. 3f, blocks 301 through 305, 307, 308, 310, 314, and 315 are as
described above. At block 316, the second spot may be assigned to
any unassigned break. This assigning of the second spot may occur
after all the spots of a particular contract line have been
placed.
[0049] With attention now directed to FIGS. 4a through 4f, these
figures represent a set of embodiments of the present disclosure,
such as may be implemented in hardware, software, computer
programs, circuitry, methodologies, etc., where like reference
numbers refer to like components/procedural stages. In FIG. 4a, an
ordered list of spots may be generated at block 401. The ordered
list of spots may be generated using an AS Order by Clause as
described elsewhere herein. At block 402 a first spot may be
selected from the ordered list. At block 403 the first spot may be
assigned to one (or more) breaks, i.e., the "first break" in any
number of ways, such as through preselection or through the use of
fixed and relative parameters for determining acceptable breaks, or
as a function of a first cost, as described elsewhere herein. The
assignment of the first spot to the first break may be made with
respect to fixed and/or relative parameters as discussed
herein.
[0050] Referring now to FIG. 4b, blocks 401 through 403 are as
described above for FIG. 4a. At block 404, the first block may be
removed from the ordered list. In FIG. 4c, blocks 401 through 403
are as described above. At block 405, a second spot may be selected
from the ordered list. At block 406, a second cost for each of the
breaks, or for only the unassigned breaks, may be determined. At
block 407 the second spot may be assigned to one (or more) of the
breaks, i.e., the "second break". The assignment of the second spot
to the second break may be made with respect to fixed and/or
relative parameters as discussed herein, or as a function of the
second cost.
[0051] With reference now to FIG. 4d, blocks 401 through 403, 405,
and 406 are as described above. At block 408 a determination may be
made as to whether any available unassigned breaks exist that meet
the criteria for placing the second spot. It may be determined that
no unassigned breaks are available for placing the second spot,
i.e., none of the unassigned breaks meet the criteria for placing
the second spot. At block 409, a determination may be made that the
ranking of the second spot is greater than the ranking of the first
spot. At block 410, the first spot may be bumped from the first
break if, for example, the ranking of the second spot is greater
than the ranking of the first spot and perhaps, for example, that
the first break meets the criteria for placing the second spot. At
block 411, the second spot may be assigned to the first break.
[0052] Relating to FIG. 4e, blocks 401 through 403, 405, 406, and
408 are as described above. At block 412 a determination may be
made that the ranking of the second spot is less than the ranking
of the first spot. At block 413, if, for example, the ranking of
the second spot is less than the ranking of the first spot, the
second spot may be placed on an exceptions list (perhaps for later
scheduling) and removed from the ordered list. Referring now to
FIG. 4f, blocks 401 through 403, 405, 406, 408, 412, and 413 are as
described above. At block 414, the second spot may be assigned to
any unassigned break. This assigning of the second spot may occur
after all the spots of a particular contract line have been
placed.
[0053] With attention now directed towards FIGS. 5a through 5k, an
example of scheduling spots in breaks according to an embodiment of
the disclosure will be described, where like reference numbers
refer to like components/procedural stages. As will be apparent,
the example described in FIGS. 5a through 5k is exemplary only and,
for simplicity's sake, makes use of only two fixed parameters and
two relative parameters. This example is in no way intended to
limit the disclosure in any way. Those of skill in the art will
readily understand that the example can be expanded to include any
number of fixed and/or relative parameters. Additionally, the
example described in FIGS. 5a through 5k may be used for any number
of spots, contract lines, networks, breaks, time divisions, days,
day parts, etc. Additionally, the costs shown are exemplary only
and in no way limit the disclosure to the specific costs
mentioned.
[0054] With the foregoing in mind, FIG. 5a depicts a simplified
representation of a break schedule to be filled with spots for a
particular network. It shall be understood that this example in no
way limits the disclosure to this particular embodiment. The grid
shown includes days of the week which are denoted in columns 500
headed by the blocks 500a through 500g labeled "M", "T", "W", "T",
"F", "S", and "S" for Monday, Tuesday, Wednesday, Thursday, Friday,
Saturday, and Sunday, respectively. Any day can be used as the
first column of the grid. Day parts are denoted by rows with
reference number 501 and may be broken down into "Overnight",
"Morning", "Afternoon", and "Prime", as shown, or by any other
denomination such as hours of the day, groups of hours, etc. As
shown in FIG. 5a, the day parts may be further subdivided into
sub-parts such that the blocks of time begin with the hour:minute
designations shown (a 24-hour clock is depicted for ease of use)
for blocks 501a through 501h, i.e., 01:15 begins the time block row
for reference number 501a, 03:45 begins the time block row for
reference number 501b, etc., through 21:15 beginning the time block
row for reference number 501h.
[0055] Referring now to FIG. 5b, exemplary fixed parameters are
applied. For this example, the fixed parameter 502 "Day of the
Week" and the fixed parameter 503 "Daypart" are used. As previously
discussed, the disclosure is in no way limited to these particular
fixed parameters. The "costs" associated with these fixed
parameters are also shown in FIG. 5b. The costs are indicative of a
desirability for placing a spot in a break within the confines of
the particular day and daypart. The Day of the Week costs for each
day are shown in blocks 502a through 502g. In this particular
example, the costs, which may be user-defined and are in no way
limited to the costs shown in this exemplary embodiment, are such
that there is a bias towards the earlier days of the week, i.e.,
the costs associated with Monday, Tuesday, and Wednesday are less
than the costs associated with the remaining days of the week. The
Daypart costs for each daypart are shown in blocks 503a through
503h. In this particular example, the costs, which may be
user-defined and are in no way limited to the costs shown in this
exemplary embodiment, are such that there is a bias towards the
"Prime" daypart, i.e., the costs associated with the two sub-parts
in the "Prime" daypart (rows 503g and 503h) are less than the costs
associated with the other dayparts/sub-parts (rows 503a through
503f). Totaling the fixed parameter costs for each row/column
results in the numbers shown for each day and daypart in the grid.
Methods other than simple totaling of the fixed parameters are
contemplated by the present disclosure.
[0056] With attention now drawn to FIG. 5c, the blocks 504 indicate
the most desirable breaks in the grid based on the two fixed costs
discussed with respect to FIG. 5b. These six blocks each have a
cost of "0" and since this is the lowest cost on the grid, these
blocks represent the breaks with the highest desirability for the
fixed factors used in this example. Similarly, the blocks 505
indicate the least desirable breaks in the grid since each of these
blocks has a cost of "30" which is the highest cost on the grid.
Preferentially, a spot to be placed will be placed in one of the
blocks 504 since those are the least cost (i.e., highest
desirability) breaks.
[0057] Now referring to FIG. 5d, a first spot is placed in block
508, which was one of the blocks 504 in FIG. 5c. Additionally, two
relative parameters are now added to the grid: "Same Day" in block
506 and "Same Daypart" in block 507. The "Same Day" relative cost
is applied to those days in which a spot has been placed, thereby
making it less desirable to place a second spot on the same day.
The "Same Daypart" relative cost is applied to those dayparts
and/or sub-parts in which a spot has been placed thereby making it
less desirable to place a second spot on the same day.
Additionally, the fixed and relative parameter costs are not
limited to nonnegative numbers so that if a negative number is
used, the desirability of a particular day and/or daypart for this
example is increased (since the cost would decrease when a negative
number is added to the existing cost for a break). The costs
associated with the "Same Day" relative parameter are shown in
blocks 506a through 506g. For this example, each of the "Same Day"
costs are set to "100". As is obvious to those of skill in the art,
the "Same Day" costs do not necessarily all have to be the same
value. Similarly, the costs associated with the "Same Daypart"
relative parameter are shown in blocks 507a through 507h. For this
example, each of the "Same Daypart" costs are set to "50". As is
obvious to those of skill in the art, the "Same Daypart" costs do
not necessarily all have to be the same value.
[0058] With continuing reference to FIG. 5d, once the first spot
("Spot 1") has been placed in the break represented by block 508,
the costs for the remaining breaks may be recalculated, this time
including the appropriate costs associated with the relative
parameters "Same Day" and "Same Daypart" with the costs associated
with the fixed parameters previously calculated. Alternatively, the
costs may be recalculated without reference to the fixed parameter
costs. In this particular example, the costs associated with the
block of time represented by block 508 is not calculated since for
this example the assumption of one spot per block, or break, is
made for the sake of simplicity without intending to limit the
disclosure to placing one spot in each day/daypart block. As shown,
the costs for blocks 509 have been recalculated by taking into
account the additional costs due to the relative parameter "Same
Daypart" since Spot 1 has been placed in the same daypart as the
blocks 509. The same recalculation is done for the blocks 511.
Likewise, the costs for blocks 510 have been recalculated by taking
into account the additional costs due to the relative parameter
"Same Day" since Spot 1 has been placed in the same day (Tuesday)
as the blocks 510. The block 512 is located in both the same day
and same daypart as Spot 1, therefore the recalculation of the cost
for block 512 includes the costs for the relative parameters "Same
Day" and "Same Daypart". The costs for the other blocks remain
unchanged since none of the other blocks are affected by the costs
for the relative parameters, i.e., none of the other blocks are in
the same day and/or same daypart as Spot 1. The result is a grid
with updated costs, where appropriate.
[0059] Referring now to FIG. 5e, it can be seen that, similar to
the analysis done with respect to FIG. 5c, the blocks 513 now
represent the most desirable breaks since the cost "10" associated
with blocks 513 is the lowest on the grid. In the same way, the
block 514 represents the least desirable break since the cost "150"
associated with this break is the highest on the grid. Therefore, a
second spot would preferentially be placed in one of the 513
(lowest cost/highest desirability) blocks. Looking now at FIG. 5f,
a second spot ("Spot 2") is placed in block 515, which was one of
the blocks 513 in FIG. 5e. Consistent with the discussion above for
FIG. 5d, the costs for the unassigned blocks/breaks are again
recalculated for the relative parameters (which are assumed, for
simplicity's sake, to be unchanged throughout this example). The
changes in the costs for each of the unassigned blocks can be
discerned by comparing the cost associated with a particular block
in FIG. 5e (the cost after placing Spot 1) with the cost for the
corresponding block in FIG. 5f (the cost after placing Spot 2).
[0060] With attention now drawn to FIG. 5g, the blocks 516
represent the most desirable breaks since the cost "15" associated
with these blocks is the lowest on the grid. In the same way, the
blocks 517 represent the least desirable breaks since the cost
"160" associated with these blocks is the highest on the grid. Now
looking at FIG. 5h, a third spot ("Spot 3") is placed in block 518,
which was one of the blocks 516 in FIG. 5g. As before, the costs
associated with the unassigned blocks are recalculated after the
placement of Spot 3 and are shown in FIG. 5h.
[0061] Now referring to FIG. 5i, the blocks 519 represent the most
desirable breaks since the cost "25" associated with these blocks
is the lowest on the grid. In the same way, the blocks 520
represent the least desirable breaks since the cost "165"
associated with these blocks is the highest on the grid. Now
looking at FIG. 5j, a fourth spot ("Spot 4") is placed in block
521, which was one of the blocks 519 in FIG. 5i. As above, the
costs associated with the unassigned blocks are recalculated after
the placement of Spot 4 and are shown in FIG. 5j. Finally, FIG. 5k
reveals that the blocks 522 represent the most desirable breaks
since the cost "60" associated with these blocks is the lowest on
the grid. In the same way, the block 523 represents the least
desirable break since the cost "175" associate with this block is
the highest on the grid. Therefore, the placement of a fifth spot
(not shown) would preferentially be in one of the blocks 522. As is
obvious to those of skill in the art, the procedure can be repeated
until either all of the spots are placed and/or all of the breaks
are occupied. It should also be obvious to those of skill in the
art that the foregoing example can be expanded to include any
number of fixed parameters, relative parameters, any value of
costs, and day and/or time divisions as desired.
[0062] Fixed parameters typically do not change when a spot is
placed. Fixed parameters may include, but are not limited to, the
following: "day of the week" which allows a particular cost to be
assigned to a particular day, "daypart" which allows a particular
cost to be assigned to a particular daypart, "used break" or
"availability" (whether a spot is placed in a break regardless if
the spot is from the same or different client, contract, or
contract line, for example) which can be used to assign costs so
that breaks are more evenly filled, and "empty break" which can be
used to assign a cost to empty breaks in order to favor breaks that
already have a spot assigned to it.
[0063] Relative parameters typically change as spots are placed.
Relative parameters may include, but are not limited to, the
following: "narrow window" which may assign a cost to a spot placed
in a same time-frame window as a previously-placed spot, such as a
15-minute window, for example, "wide window" which may assign a
cost to a spot placed in a same time-frame window as a
previously-placed spot, such as a 60-minute window, for example,
"daypart" or "same daypart" which allows for a cost to be assigned
to the breaks in a daypart for which a previous spot has been
placed, "same day" which allows for a cost to be assigned to the
breaks in a day for which a previous spot has been placed, "same
day+n" which is similar to "same day" where the "same day" cost is
expanded to n days either side of a placed spot, and "preferred
product separation" which assigns costs to those breaks close to a
previously-assigned break for a spot for a particular product or
company so as to maintain a separation in time from the
previously-assigned break.
[0064] Referring now to FIG. 6, reference number 600 refers to an
exemplary graphical user interface, according to an embodiment of
the disclosure, showing an example of a status summary display
according to an embodiment of the disclosure. Broadcast zones 601
and networks 602 form a grid for which jobs 603 can be entered to
give an operator a quick-look overview of the status of placing
spots. Status summary settings 604 may be used by the operator to
change the parameters of the display grid.
[0065] With attention now drawn to FIG. 7, the exemplary graphical
user interface 700 represents an input screen according to an
embodiment of the disclosure. The various inputs on screen 700 may
be user-configurable and the values entered may be set by the user.
The input screen may include network settings 701 for setting
parameters for scheduling on a particular network, as indicated at
705, and may include, but is not necessarily limited to,
"NumWeeksToSchedule" for setting the number of weeks to schedule
spots on the particular network, "NumWeeksToNotAllowOSPC" for
setting the number of weeks in "NumWeeksToSchedule" to allow
oversold and product conflicts ("OSPC") in the schedule,
"DailyProgramChangeCutoff" for setting the number of hours prior to
scheduling for the system to stop importing network programming
updates, "SchedulingTimePeriods" for setting time periods when the
adaptive scheduler can run, e.g., it may be desirable to not allow
the scheduler to run during a particular time when it is
anticipated that changes will be made to some of the parameters,
"FixSchedule" for setting the time when the scheduling will be
completed, "HoursToRequireCopy" for setting the number of hours the
system should require advertising copy for scheduling spots,
"WeekendOverrideDay" for setting the day of the week to stop
program changes, contract changes, and/or require copy for the
weekend and/or the following Monday, for example, and
"RescheduleCutoff" (not shown) for designating a time after which
spots that need to be rescheduled for the current day, for example,
will be allowed to be rescheduled.
[0066] With continuing attention to FIG. 7, the input screen of the
exemplary graphical user interface 700 may also include break
selection 702 for setting fixed factors (fixed parameters). The
fixed factors may include, but are not limited to, "MondayCost" for
setting the cost associated with a break occurring on a Monday,
"TuesdayCost" for setting the cost associated with a break
occurring on a Tuesday, "WednesdayCost" for setting the cost
associated with a break occurring on a Wednesday, "ThursdayCost"
for setting the cost associated with a break occurring on a
Thursday, "FridayCost" for setting the cost associated with a break
occurring on a Friday, "SaturdayCost" for setting the cost
associated with a break occurring on a Saturday, "SundayCost" for
setting the cost associated with a break occurring on a Sunday,
"UsedBreakCost" for setting costs to favor scheduling spots evenly,
"EmptyBreakCost" for setting costs to favor scheduling spots in
breaks that already have a spot scheduled. and "DayPartCost" (not
shown) for assigning costs to particular dayparts, as discussed
previously.
[0067] Still with continuing attention to FIG. 7, the input screen
of the exemplary graphical user interface 700 may also include
break selection 703 for setting relative factors (relative
parameters). The relative factors may include, but are not limited
to, "NarrowWindowSize" for setting an amount of time that two
spots, typically, but not necessarily, for the same client and/or
same contract, are placed within each other for the day being
scheduled based on historical spot placement, "NarrowWindowCost"
for setting a cost to a break in the NarrowWindowSize, i.e., a same
time-frame window as a previously-placed spot, such as a 15-minute
window, for example, typically, but not necessarily, for the same
client and/or same contract, "RelativeDaypartCost" for setting a
cost to be assigned to the breaks in a daypart for which a previous
spot, typically from the same client, has been placed,
"WideWindowSize" for setting an amount of time that two spots,
typically, but not necessarily, for the same client and/or same
contract, are placed within each other for the day being scheduled
based on historical spot placement, "WideWindowCost" for setting a
cost to a break in the WideWindowSize, i.e., a same time-frame
window as a previously-placed spot, such as a 60-minute window, for
example, typically, but not necessarily, for the same client and/or
same contract, "SameDayCost" for setting a cost to a break
occurring in the same day as another spot previously placed, where
the previously-placed spot typically, but not necessarily is for
the same client and/or same contract, "SameDayPlus1Cost" for
setting a cost to breaks occurring in the day immediately preceding
or immediately following the day a previously-placed spot occurs,
where the previously-placed spot typically, but not necessarily is
for the same client and/or same contract, "ProductSeparationSize
(min)" for setting an amount of time that two spots for the same
product, for example, may be placed within each other for the day
being scheduled based on historic spot placement, and
"ProductSeparationCost" for setting a cost for breaks within the
"ProductSeparationSize (min)" time frame.
[0068] With further attention to FIG. 7, the input screen of the
exemplary graphical user interface 700 may also include system
settings 704 for setting systems parameters. The system parameters
may include, but are not limited to, "ASMaxOversold (sec)" which
designates the maximum number of seconds, for example, that can be
shown as over sold or have a product conflict in a time frame
(e.g., a week) that allow over selling and/or product conflicts,
""NumWeeksToNotAllowCreditHold" which designates a number of weeks
within NumWeeksToSchedule (in the network settings 701 described
above) to allow spots to be scheduled from contracts that are in a
status of credit hold, "ASCheckforLogs" to disallow spots from
being scheduled when a playlist has been previously generated,
"BalanceAdCopyDays" may be a true/false entry choice for preventing
front-loading of spots during scheduling due to expiring ad copy,
"UseDatedCopyGroups" which enables a feature that allows a user to
provide copy start and stop dates within a rotation pattern that
may be different than the ad copy library dates,
"BreakSelectionNumofWeeks" (not shown) which designates the number
of weeks worth of historical spot placement data to consider when
calculating break scheduling values, "ASOrderByClause" which, as
discussed above, may be used in the determination of the order in
which spots are placed by, for example, ordering the various
contract lines and/or ordering the various spots to be placed
within one or more contract lines, "ProductSeparation (min)" which
designates the number of minutes that need to occur between spots
that are associated with the same or similar product type,
"ClientSeparation (min)" which designates the number of minutes
that need to occur between spots that are associated with the same
client, "AdsPlotterWaitInterval (sec)" (not shown) which designates
how often the scheduler will attempt to look for contract lines
that need to be scheduled, "AdsPlotterSPTimeOut (sec)" (not shown)
which designates how long a database process will run before
stopping and producing and error, and
"AdsPlotterSchedulingBreaksReq" (not shown) which designates the
number of breaks that must be in the system for a given week, for
example, before scheduling will occur.
[0069] Considering now FIG. 8, a detail screen 800 is illustrative
of an exemplary graphical user interface, according to an
embodiment of the disclosure. The screen 800 may include a Contract
Detail section 805 which may include, but is not necessarily
limited to, columns for "ConID" (contract identification),
"Client", "Primary Reference", "Secondary Reference", "Contract
Remarks", "Zone", "Network", "Mod Date" (modification date), "#
Spots" (number of spots to be scheduled), and "Cost". A first
contract line 801 is shown with information for the above-mentioned
columns and a second contract line 802 is shown with similar
information. The screen 800 may also include an Interconnect Detail
section 806 which may include, but is not necessarily limited to,
columns for "InterConID" (interconnect identification), "Zone",
"Network", and "Mod Date" (modification date). A first interconnect
line 803 is shown with information for the above-mentioned columns
and a second interconnect line 804 is shown with similar
information.
[0070] Referring now to FIG. 9. a job status screen 900 is shown
which is illustrative of an exemplary graphical user interface
according to an embodiment of the disclosure. The job status screen
900 may include, but is not necessarily limited to, columns for
"JobID" (job identification", "Week #" (week number), "Status",
"Rank", "Zone", "Network", "Run Date", and "Run Time". The grid on
screen 900 can be coded by the job status indicators 901 to give
the users a quick over view of the status of the jobs in the
scheduler.
[0071] With attention now directed towards FIG. 10, scheduling
system according to an embodiment of the disclosure is shown in
block diagram form. A database 1001 may include an ordered list of
spots to be scheduled, where each spot may have an associated
scheduling factor, and a plurality of breaks for one or more
networks. A microprocessor 1002 may be operatively connected to the
database 1001 and a display device 1003. The microprocessor may
include circuitry for selecting one of the spots from the database
1001, circuitry for determining a first cost for each of the breaks
in the database 1001 as a function of a predetermined algorithm,
and circuitry for assigning the first spot to one (or more) of the
breaks which has a lowest first cost or that has a first cost that
is less than a first predetermined amount. The predetermined
algorithm may determine the first cost as a function of a
predetermined fixed parameter, as described herein. The
microprocessor 1002 may also include circuitry for removing the
first spot from the ordered list in the database 1001. Furthermore,
the microprocessor 1002 may include circuitry for selecting a
second spot from the database 1001, which may be the same as the
circuitry for selecting the first spot, circuitry for determining a
second cost for unassigned breaks in the database 1001 as a
function of the first cost and as a function of a predetermined
relative parameter, as described herein, and circuitry for
assigning the second spot to one of the unassigned breaks in
database 1001 which has a lowest second cost or has a second cost
that is less than a second predetermined amount, which may be the
same as the circuitry for assigning the first spot. Additionally,
the circuitry for assigning the second spot may determine that no
unassigned breaks in the database 1001 have a second cost less than
a second predetermined amount thereby preventing the second spot
from being assigned to one of the unassigned breaks in database
1001, and the circuitry may determine that the second spot has a
ranking greater than a ranking for the first spot, bump the first
spot from the first break, and assign the second spot to the first
break.
[0072] Still further, the circuitry for assigning the second spot
may determine that no unassigned breaks have a second cost less
than a second predetermined amount thereby preventing the second
spot from being assigned to one of the unassigned breaks in the
database 1001, and may determine that the second spot has a ranking
less than a ranking for the first spot, place the second spot on an
exceptions list, and remove the second spot from the ordered list
of spots.
[0073] Yet further, the circuitry for assigning the second spot may
assign the second spot to any one of the unassigned breaks in the
database 1001. Additionally, the microprocessor 1002 may include
circuitry for assigning ad copy to each of the first and second
spots.
[0074] The display device 1003 may be an electronic display device,
such as an LCD (liquid crystal display) screen, a CRT (cathode ray
tube), or other similar display device, as is known in the art. The
display device may also be a printer for printing out, rather than
displaying, the results of the operation of the scheduling system.
The display device 1003 may display/print out any or all of the
screens shown in FIGS. 6 through 9.
[0075] The above description is not intended and should not be
construed to be limited to the examples given but should be granted
the full breadth of protection afforded by the appended claims and
equivalents thereto. Although the disclosure is described using
illustrative embodiments provided herein, it should be understood
that the principles of the disclosure are not limited thereto and
may include modification thereto and permutations thereof.
* * * * *